Planned vs Actual
The Planned vs Actual
functionality of the Gantt allows you to compare actual start
and end
dates to originaly planned dates. If the actual completion date of a task matches the planned end time date, the default task appearance is used. In the scenarios listed below, when there is a difference between an actual and a planned date, the Gantt visualizes it by changing the appearance of the task:
- The actual
end
date of the task is before the plannedend
date - the task is colored green. - The actual
end
date of the task is after the plannedend
date - a hatched bar that marks the delay is rendered in the task. - The actual
start
date of the task is after the plannedend
date - the task is colored red.
For a full example of the Planned vs Actual functionality, refer to the Planned vs Actual Demo
Configuration
The example below demonstrates how to configure the Gantt to display planned and actual dates.
<div id="gantt"></div>
<script>
var gantt = $("#gantt").kendoGantt({
dataSource: tasksDataSource,
views: [
"day",
{ type: "week", selected: true },
"month"
],
columns: [
{ field: "title", title: "Title", editable: true, sortable: true, width: 200 },
{ field: "start", title: "Actual Start Date", format: "{0:M/d/yyyy}", width: 85 },
{ field: "end", title: "Actual End Date", format: "{0:M/d/yyyy}", width: 85 },
{ field: "plannedStart", title: "Planned Start Date", format: "{0:M/d/yyyy}", width: 85 },
{ field: "plannedEnd", title: "Planned End Date", format: "{0:M/d/yyyy}", width: 85 },
],
showPlannedTasks: true,
toolbar: [
"plannedTasks"
],
editable: { plannedTasks: true },
snap: false
}).data("kendoGantt");
</script>
The plannedTasks
tool set in the toolbar
option enables a switch in the toolbar of the Gantt that allows toggling the Planned vs Actual
functionality.
The showPlannedTasks
configuration controls whether planned dates will be shown initially.
Through the editable
configuration, you can allow or prevent editing of planned tasks.